A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
Options :
3
9
27
81
Answer :
9
Solution :
σ1, σ2, ...., σ8, σ9 = 3
σcp =
σcp =
σcp = = 9
∴ the standard deviation of the critical path is 9.