Question

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is __________ weeks (in integer).

Activity Time estimates (in weeks) Immediate predecessor(s) Optimistic time Most likely time Pessimistic time A 4 5 6 None B 1 3 5 A C 1 2 3 A D 2 4 6 C E 3 4 5 B, D

Activity Time estimates (in weeks)
Immediate
predecessor(s)
Optimistic
time
Most likely
time
Pessimistic
time
A 4 5 6 None
B 1 3 5 A
C 1 2 3 A
D 2 4 6 C
E 3 4 5 B,D
Show Answer

Answer :

Correct answer is : 15

Report
More Similar Tests

Related Tests