Question

Aproject consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:

Activity
Immediate predecessor
Estimated duration (weeks)
P
5
Q
1
R Q
2
S P,R
4
T P
6
U S,T
3

If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is ___________.

Show Answer

Answer :

6

Hence different paths are:

P—T-U=5+6+3= 14 weeks < Critical path

P—Dummy -S—U=5+4 +3 = 12 weeks

Q-R-S-U=1+2+3+4=10 weeks

Only ‘S’ is delayed and no other activity is delayed.

So, maximum activity time for activity ‘S’ can be 6 weeks without delaying the project.