Question
Aproject consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
| Activity |
Immediate
predecessor
|
Estimated duration
(weeks) |
| P | 5 | |
| Q | 1 | |
| R | Q |
2 |
| S | P,R |
4 |
| T | P |
6 |
| U | S,T |
3 |
If all the activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is ___________.