Question

Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is __________ hours.

Part Milling (hours) Polishing (hours)
P1 8 6
P2 3 2
P3 3 4
P4 4 6
P5 5 7
P6 6 4
P7 2 1

Options :

  1. 31

  2. 33

  3. 30

  4. 32

Show Answer

Answer :

33

Solution :

According to Johnson's algorithm, optimum job sequence is,

P3 → P4 → P5 → P1 → P6 → P2 → P7

Part Miling ( hours) Polishing (hours)

In time Processing
time
Out time In time
Processing
time
Out time
P3 0 3 3 3 4 7
P4 3 4 7 7 6 13
P5 7 5 12 13 7 20
P1 12 8 20 20 6 26
P6 20 6 26 26 4 30
P2 26 3 29 30 2 32
P7 29 2 31 32 1 33

The minimum total completion time required for carrying out both the operations for all 7 parts is 33 hours.