Question

Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is ___________ (correct to two decimal places).

Job Processing time (days)
Due date (days)
A 3 8
B 7 16
C 4 4
D 9 18
E 5 17
F 13 19
Show Answer

Answer :

6.33

By STP rule


Job PTDDJob FlowTime
Tardiness
A 380+3 = 3 0
B 443+4= 7
3
C 5177+5 = 12 0
D 71612+7 = 19 3
E 91819+9 = 28 10
F 131928+13 = 41 22




38

Total tardiness = 38

Average tardiness per job = Total tardiness / No. of jobs = 38/6 = 6.33 days