Question
The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ________ weeks
Activity | Duration (Weeks) | Precedence Relationship |
A | 5 | A<B,C,D |
B | 7 | B<E,F,G |
C | 10 | C<I |
D | 6 | D<G |
E | 3 | E<H |
F | 9 | F<I |
G | 7 | G<I |
H | 4 | H<I |
I | 2 | --- |
Options :
17
21
23
25
Copyright © 2025 Test Academy All Rights Reserved