The activities of a project, their duration and the precedence relationships are given in the table. For example, in a precedence relationship “X < Y, Z” means that X is predecessor of activities Y and Z. The time to complete the activities along the critical path is ________ weeks




Activity Duration (Weeks) Precedence Relationship
A 5 A<B,C,D
B 7 B<E,F,G
C 10 C<I
D 6 D<G
E 3 E<H
F 9 F<I
G 7 G<I
H 4 H<I
I 2 ---

Options :

  1. 17

  2. 21

  3. 23

  4. 25

Show Answer

Answer :

23

Solution :


So critical path is A - B - F - I

Critical path duration = 23 weeks