Question

With reference to the Economic Order Quantity (EOQ) model, which one of the options given is correct?


Options :

  1. Curve P1: Total cost, Curve P2: Holding cost,

    Curve P3: Setup cost, and Curve P4: Production cost.

  2. Curve P1: Total cost, Curve P2: Holding cost,

    Curve P3: Setup cost, and Curve P4: Production cost.

  3. Curve P1: Production cost, Curve P2: Holding cost,

    Curve P3: Total cost, and Curve P4: Setup cost.

  4. Curve P1: Total cost, Curve P2: Production cost,

    Curve P3: Holding cost, and Curve P4: Setup cost.

Show Answer

Answer :

Curve P1: Total cost, Curve P2: Holding cost,

Curve P3: Setup cost, and Curve P4: Production cost.

Report
More Similar Tests

Related Tests